Project Description

Overview

The Alphington Trunk Sewer Replacement, which services some 85,000 homes, was a major upgrade of essential sewerage infrastructure in the area for the existing old brick sewer which was deteriorated significantly due to a century of use. The replacement section of sewer integrates with the existing sewer operated by Melbourne Water and the reticulation system operated by Yarra Valley Water.

Rob Carr Pty Ltd was engaged by Lend Lease Engineering to undertake the construction of approximately 1km of pipeline via Microtunnelling over 4 separate drives. Drive lengths varied between 80m for the DN700 line and 587m for the DN1500 line. To facilitate the TBM launch and reception as well as construction of detailed complex concrete maintenance structures (DN5000) and detailed connections to existing assets, Rob Carr constructed access shafts to depths of up to 16m and 9m in diameter.

Varying methodologies were used to construct the access shafts with consideration given to ground type, strength and location within the environmentally sensitive park zone. Underpinned caissons were the preferred choice for the deep shafts in the confined locations with traditional methods used for the shallower shafts. The most challenging aspect of this particular project was the construction of a single 587m drive using DN1500 reinforced concrete jacking pipe, which was installed on a curved alignment to facilitate the installation of the pipeline within critical stakeholder boundaries. A second 272m drive was also installed on a curved alignment to complete the DN1500 section of the work. This 2nd drive was also constructed through existing infrastructure at key points, which necessitated the diversion of major sewage flows during this time. Rob Carr Pty Ltd used its TCS 1500 Iseki TBM to successfully construct the two curved drives on the major section of the work, which was custom built to suit the 300 MPa native rock found throughout portions of the alignment.

Client:
Lend Lease Engineering

Location:
Melbourne, VIC

Type of contract:
Construct Only

Value Range:
$10 million – $15 million

Construction period:
Jun 2014 – Aug 2015

0m
Total Drive
0m
Max Drive
0
TBM

Related

Markets:

Capabilities:

Brochure

Similar projects

You have a project?

Rob Carr widely operates in
Australia and New-Zealand…

…through multiple offices in
Sydney, Brisbane, Perth and Auckland.

Contact us

You have a project?

Rob Carr widely operates in
Australia and New-Zealand…

…through multiple offices in
Sydney, Brisbane, Perth and Auckland.

 

Contact us