Project Description

Overview

The Melbourne Metro Tunnel is a major enhancement to Melbourne’s rail network which will need to integrate with the existing system. As part of the overall strategy, it was imperative that engagement and delivery of the early works portion was undertaken to facilitate critical utility service relocation including protection and relocation of utility services such as gas, sewer and water mains, demolition and road, bicycle and footpaths to allow for the commencement of the major infrastructure works.

These works specifically related to part of the proposed scope being undertaken as the PPP interface works at Domain Station which required the realignment of a portion a major sewer owned by Melbourne Water. The sewer was inappropriately located for the ensuing PPP (Station Box & Tunnel) works. Rob Carr was engaged by John Holland (the Managing Contractor for the early works) to intercept the existing DN1905 brick South Yarra Main Sewer (SYMS), and make 2 new connections at Domain Road and Albert Street. These live tie in works between shafts into the existing 100 year old brick sewer were conducted some 20 metres below ground.

The new 1920mm OD sewer was tunnelled under St Kilda Road for 161m between those connections. The tunnel was a single straight pipe jacked drive at 1:1500 grade to points upstream and downstream of the proposed station box with the new sewer installed and commissioned prior to the installation of the D Walls by the PPP Contractor for the station box. The existing brick main, was then decommissioned and grouted. The new wastewater infrastructure works constructed by Rob Carr also included the excavation and installation of ring beams to 4 deep shafts up to 20m in depth. The work was conducted in dense urban conditions under live road and rail needing to achieve a tight project time frame. The project was a finalist for a ‘Project Excellence’ award at the CCF Victoria 2018 awards.

Client:
John Holland

Location:
Melbourne, VIC

Type of contract:
Construct Only

Value Range:
$2 million – $5 million

Construction period:
Jun 2017 – Dec 2017

0m
Max Single Drive
0
Secant Piled Shafts
0m
Deep Shafts
Brochure

Similar projects

You have a project?

Rob Carr widely operates in
Australia and New-Zealand…

…through multiple offices in
Sydney, Brisbane, Perth and Auckland.

Contact us

You have a project?

Rob Carr widely operates in
Australia and New-Zealand…

…through multiple offices in
Sydney, Brisbane, Perth and Auckland.

 

Contact us